Build activity from Preliminary Design until Civil Mechanical & Electrical Implementation
Setting up the infrastructure to install a radio transmission which functioned as a signal sender / receiver.
Process Preliminary Design - Civil Mechanical & Electrical Implementation
Preliminary Design (Soil Test) - Get Sample of soil from Proposed Foundation Area : (Boring Log) and Soil Penetration : (Cone Penetration Test)
- Foundation Design Analysis and As Plan Drawing
- Preliminary Construction (Setting Out/ Uitzet/ Bouwplank) : Implement As Plan Drawing in to actual location
- Excavation for Tower Foundation :
- Tower Foundation
- Back Fill Soil after foundation
- Tower Erection + Antenna mounting: Install Tower from section 1 until top section. In this work need group of team called Erector Team. They must have special skill and sertificat in Working at Height. Safety tool are very important, before Tower erection start they must wear safety tools.
- Landscaping (Fence Foundation and Bracing Fence)
- RBS Foundation or BTS Foundation or Shelter Foundation
- Grounding installation (Box control, Down Conductor and Perimeter)
- Electrical Installation (KWH Pole Foundation, KWH Pole, ACPDB Pole, others)
- Landscaping (Gravel)
- PLN Connection (Electricity from PLN)
- Prepare As Built Drawing (Actual Drawing according to final site condition)
- Site Binder (Collect all document for approval) Document approved, execute payment to Land Lord
- Status site is Ready For Installation (RFI)
ITC - Install Radio and Antenna