Site
Acquisition is s series of activities to prepare a New Location for BTS (Base Transceiver System) or Telecommunications Tower until New Location Ready For Construction (RFC) or Civil Mechanical and Electrical (CME) Process.
There are
two methods of Land acquisition/ Site Acquisition (SITAC):
Tower Provider or Operator need land to Build BTS (Base Transceiver Station).
- Lease the land : Both party (Tower Provider or Operator and Land Lord) have agreement at least for 5 (five) - 10 (ten) years.
- Buy the land : If the budget match with business value calculated by Tower Provider Team Management.
Tower Provider or Operator need land to Build BTS (Base Transceiver Station).
- Define Nominal Coordinate of Site : The whole plan of Tower Provider or Operator is to accommodate market demand in Telecommunications. They need to plot new BTS at several integrated places.
- Find 3 Candidate by preparing SSR / ESR / TSSR : After they get approval from their system, they start to have Site Survey Report (SSR) at 3 candidate near the Nom (usually is about 100 m - 500 m from Nom). From 3 candidate, they choose the best candidate.
- Prepare Lost Survey Report of candidates : To ensure the places are the right places to build new BTS. They must have Lost Survey Report in one area (called nominal - one point with coordinate). The will get data from Nom to calculate in their system.
- Choose one the best candidates : after they review prices and location, and then continue with Acquisition Process.
- Prepare Acquisition Document (BAN, BAK and Owner's Land Certificate - SHM / HGB / parcels / girik), SPPT / UN, History Land Letter, Statement of No Dispute / Not for collateral in the Bank, Letter of Approval Husband / Wife, Family Approval, Approval Letter Access Road, giving authorization letter (if authorized), ID cards of recipients devolution, Plan Houses Residents Around the Tower.
- Site Binder (Collect all documentation for approval)
- Document approved, execute payment to Land Lord.
- Status site is RFC