In Business Telecommunication, provide the best place to Build a BTS (Base Transmission Station) which can support Telecommunication Operator maximized their need of costumer demand. Their solution is preparing a Location by follow the procedure starting with Sitac(Site Acquisition) and CME- Civil Mechanical and Electrical and then continue with Transmission Installation.
Site
Acquisition is to prepare a new BTS location Ready For Construction (RFC).
Sitac
Officer can provide it by land leasing or buying a land.This phase is a crucial part of preparation work needed to Build a BTS.
Beside of Sitac works, Permit from Government (IMB) is also a requirement Document
Process
of Site Acquisition
- Define Nominal Coordinat of Site to find candidates
- Find in specific range 3 Coordinate of Candidate and prepare SSR / ESR / TSSR. SSR (Site Survey report), ESR (Engineering Survey report) and TSSR (Technical Site Survey Report)
- Verification by Operator (Planning Division)
- Prepare Lost Survey Report of candidate
- Choose one the best candidates (Verified by Operator, Passed LOS Survey and Best Price)
- Prepare Acquisition Document(BAN, BAK and Owner's Land Certificate - SHM / HGB / parcels / girik), SPPT / UN, History Land Letter, Statement of No Dispute / Not for collateral in the Bank, Letter of Approval Husband / Wife, Family Approval, Approval Letter Access Road, giving authorization letter (if authorized), ID cards of recipients devolution, Plan Houses Residents Around the Tower.
- Site Binder (Collect all document for approval)
- Document approved, excecute payment to Land Lord.
- Status site is RFC
CME- Civil Mechanical and Electrical
Build activity from Pre Design until CME Implementation
Process Pre Design - CME Implementation
Build activity from Pre Design until CME Implementation
Process Pre Design - CME Implementation
- Pre Design (Soil Test)
- Foundation Design Analysis and As Plan Drawing
- Pre Construction (Prepation and Measurement)
- Excavation for Tower foundation
- Tower Foundation
- Back Fill Soil after foundation
- Tower Erection + Antenna mounting
- Landscaping (Fence Foundation and Bracing Fence)
- RBS Foundation or Shelter Foundation
- Grounding installation (Box control, Down Conductor and Perimeter)
- Electrical Installation (KWH Pole Foundation, KWH Pole, ACPDB Pole, others)
- Landscaping (Gravel)
- PLN Connection (Electricity from PLN)
- Prepare As Built Drawing (Actual Drawing according to final site condition)
- Site Binder (Collect all document for approval)
- Document approved, execute payment to Land Lord.
- Status site is ready For Installation (RFI)
ITC - Install Radio and Antenna