Build a BTS (Base Transceiver Station)

In Business Telecommunication, provide the best place to Build a BTS (Base Transmission Station) which can support Telecommunication Operator maximized their need of costumer demand.
Their solution is preparing a Location by follow the procedure starting with Sitac(Site Acquisition) and CME- Civil Mechanical and Electrical and then continue with Transmission Installation.


Site Acquisition is to prepare a new BTS location Ready For Construction (RFC).
Sitac Officer can provide it by land leasing or buying a land.
This phase is a crucial part of preparation work needed to Build a BTS.
Beside of Sitac works, Permit from Government (IMB) is also a requirement Document

Process of Site Acquisition
  • Define Nominal Coordinat of Site to find candidates
  • Find in specific range 3 Coordinate of Candidate and prepare SSR / ESR / TSSR. SSR (Site Survey report), ESR (Engineering Survey report) and TSSR (Technical Site Survey Report)
  • Verification by Operator (Planning Division)
  • Prepare Lost Survey Report of candidate
  • Choose one the best candidates (Verified by Operator, Passed LOS Survey and Best Price)
  • Prepare Acquisition Document
    (BAN, BAK and Owner's Land Certificate - SHM / HGB / parcels / girik), SPPT / UN, History Land Letter, Statement of No Dispute / Not for collateral in the Bank, Letter of Approval Husband / Wife, Family Approval, Approval Letter Access Road, giving authorization letter (if authorized), ID cards of recipients devolution, Plan Houses Residents Around the Tower.
  • Site Binder (Collect all document for approval)
  • Document approved, excecute payment to Land Lord.
  • Status site is RFC

CME- Civil Mechanical and Electrical
Build activity from Pre Design until CME Implementation

Process Pre Design - CME Implementation
  • Pre Design (Soil Test)
  • Foundation Design Analysis and As Plan Drawing
  • Pre Construction (Prepation and Measurement)
  • Excavation for Tower foundation
  • Tower Foundation
  • Back Fill Soil after foundation
  • Tower Erection + Antenna mounting
  • Landscaping (Fence Foundation and Bracing Fence)
  • RBS Foundation or Shelter Foundation
  • Grounding installation (Box control, Down Conductor and Perimeter)
  • Electrical Installation (KWH Pole Foundation, KWH Pole, ACPDB Pole, others)
  • Landscaping (Gravel)
  • PLN Connection (Electricity from PLN)
  • Prepare As Built Drawing (Actual Drawing according to final site condition)
  • Site Binder (Collect all document for approval)
  • Document approved, execute payment to Land Lord.
  • Status site is ready For Installation (RFI)